Reconstruction of the footbridges of mole 3 of the Lavera oil terminal

At mole 3 of the Lavéra oil terminal, rebuilding of the concrete supports and installation of 5 steel decks of 30 m x 5 m. 4 decks are new and one of the decks (more recent) has been removed, repairs have been carried out and the anti-corrosion treatment has been redone before installation. Work carried out during shutdowns with pipelines in operation in the immediate vicinity of the worksite.

Date
2013
localisation
Lavera, France